The
Right of Way in transmission line defined as land set two path of the center of
transmission line. Right of Way also
name as transmission corridor and this corridor maintain from private or
government authorities who do the maintenance works. Safety is one of the essential factor of
transmission line and ROW provide necessary landscape arrangement. There are several voltage levels of the
lines maintained and the width of transmission line corridor (ROW) changes due
to the voltage levels.
For
example, 132kV transmission line Right of Way shall nearly 30m which means 15m
either side from the center of 132kV transmission lines
For
higher voltages transmission line the width or transmission line get increased
to maintain proper safety clearance.
Normally trees which grow higher will cut for example in generally trees
which higher than 3m will cut to maintain proper ROW under transmission line
and trees or plant can grow below 3m,
The condition and clearance height may different from country to country.
ROW
in one of the major consideration while creating transmission line. Since most of transmission line traverse
overhead most of vegetation affect for
transmission line corridor and social and environmental study is very necessary
while design of transmission lines.
Environmental
and social impacts of transmission lines are much less compare to other major
developments but in some cases there transmission line corridor do major
impacts in environmental sensitive areas.
Following
are most commonly used ROW parameters for transmission lines
ROW
width for 132kV transmission line = 27m
ROW
width for 220kV transmission line = 35m
ROW
width for 400kV transmission line = 53m
ROW
width for 765kV transmission line = 85m